Fernandina Beach sand placement starts this week

Published Feb. 14, 2017

JACKSONVILLE, Fla. – The U.S. Army Corps of Engineers, Jacksonville District announced today that a portion of Fernandina Beach will soon receive much-needed sand as part of the Kings Bay Entrance Channel maintenance project.

The Corps awarded the dredging contract in December to Manson Construction Co. of Seattle, Washington, for approximately $23.6 million.

Sponsored by the Naval Submarine Base Kings Bay, the project is critical to commercial cargo transiting the port and also to the Navy base, which shares the entrance channel.  

 The project includes maintenance dredging of the entrance channel and parts of inner channel, returning the project to its authorized dimensions.  It also includes beneficial placement of beach compatible sand at Fort Clinch State Park and the northern portion of Fernandina Beach in Nassau County.  The contractor completed sand placement at Fort Clinch on Monday and starts work at Fernandina Beach this week.  Sand placement at Fernandina Beach will take a few weeks.  Managing sediment results in significant cost savings and environmental benefits.

The project helps off-set natural erosion at Fort Clinch while the groins help protect the fort from the dynamic water-flow. Manson Construction placed an estimated 100,000 cubic yards of sand at Fort Clinch beach.

 The contract originally had two alternative placement areas for Fernandina Beach: Alternative A – from Jasmine Street (where most Hurricane Matthew erosion occurred) to approximately Sadler Road, and Alternative B – from Kimberly Street to Dolphin Avenue.  Contract bid costs came in higher than available funding to transport sand so far down the beach, so the Corps awarded Alternative B with the northern placement area.

 The awarded beach placement area starts near Fort Clinch State Park’s coastal boundary and can go as far south as Dolphin Avenue.  However, the placement will move from north to south until all material runs out, so it may not reach all the way to Dolphin Avenue.  The Corps estimates the contractor will place about 150,000 cubic yards at Fernandina Beach.  This beach location has benefitted from the Kings Bay Entrance Channel project sand placement for many years and the benefits were seen post Hurricane Matthew.  The beach didn't suffer much erosion, unlike other areas to the south that aren’t nourished on a regular basis.

 The contractor will disperse about 1.1 million cubic yards of non-beach compatible sand between the approved nearshore disposal area and an offshore disposal site.

 Corps officials say dredging will end no later than March 31, which is the end of the environmental turtle window allowing hopper dredging. 

 

-30-


Contact
Susan Jackson
904-232-1630
Susan.J.Jackson@usace.army.mil
or
Amanda Parker
904-232-1576
amanda.d.parker@usace.army.mil

Release no. 17-006