Date |
Meeting Subject |
Location |
Goals/Objectives/Materials |
|
|
|
|
January 18, 2017 |
Reconnaissance Survey |
Teleconference |
Review of draft Reconnaissance Survey protocol by IWG. No meeting notes. Changes were made directly to the protocol.
- Agenda
- PE ESA Survey Plan Draft 112116
- PE ESA Survey Plan Draft 112616 with NMFS comments
- Draft PE Reconnaissance Plan 122116
- PE Proposed Reef Reconnaissance Survey Map
|
January 20, 2017 |
ESA Survey |
Teleconference |
Reviews of draft ESA Survey protocol by IWG. No meeting notes. Changes were made directly to the protocol.
- Email re Port Everglades ESA Survey Plan Review
|
February 21, 2017 |
Monitoring Plan |
Teleconference |
* NEPA Scoping
* Review components of a monitoring plan
* Identify areas requiring more in-depth discussions
* Schedule future meeting to start in-depth discussions
- Agenda
- Meeting Notes Final
|
May 17, 2017 |
Particle Tracking Module - Update |
Teleconference |
Goal of meeting was to answer questions and review dredging scenarios for the Particle Tracking Model. No meeting notes.
- Port Everglades Sediment Transport Model
|
May 23, 2017 |
Project Update |
Teleconference |
* Update to the IWG on the status of the Port Everglades Navigation Improvement Project
* Continue regular communication with the IWG
* Project transparency
- Agenda
- Meeting Notes
|
October 19, 2017 |
Project Update |
Teleconference |
IWG update on the status of various aspects of the PENIP.
- Meeting Notes Final
|
November 9, 2017 |
ESA Survey Protocol |
Teleconference |
Resolution of how to fulfill the ESA Listed Coral Species Survey Study Plan product: "Total acres of hardbottom habitat that were directly surveyed by the protocol."
- Meeting Notes Final
|
November 15, 2017 |
Calculation of Hardbottom percentages of ESA Listed Coral Species Survey Sites for Port Everglades |
Teleconference |
For all participants to fully understand how DCA used the comment section of the data sheets and the Excel spreadsheets to calculate percent hardbottom for the ESA survey.
- ESA Discussion handout
- Meeting Notes Final
|
December 1, 2017 |
IWG Meeting (numerous updates and topics) |
Teleconference |
Project overview:
* Recon survey status
* ESA survey status
* Revised Walker Maps Background Paper status
* Review of roles of Sediment Transport Model and Particle Tracking Model
* Revised project timeline
* Potential Sediment Deep Water Placement Site
- Agenda
- Meeting Notes
|