Date  Meeting Subject  Location Goals/Objectives 
 
       
July 26, 2016                                Initial meeting                    Orlando, FL                                

A kick-off and initial meeting of the Port Everglades (PE) IWG held to build the team and focus on development of the PE NIP Monitoring and Adaptive Management Plan. 

  1. Agenda
  2. Presentation - Lessons learned from PortMiami 
  3. Presentation - PE NIP
  4. Presentation - Conflict Resolution 
  5. EPA Issues of Concern - Page 1
  6. EPA Issues of Concern - Page 2
  7.  Draft Outline of DEP Suggested Biological Monitoring
  8.  Meeting Notes Final
August 10, 2016 Sediment Model Teleconference

Sediment Model Webinar

  1. Meeting Notes Final
August 16, 2016    
  1. Construction Methodologies
  2. Dredging Scenarios
August 19, 2016 Reconnaissance Survey Webinar
  1. Agenda
  2. Meeting Summary and Tasks
September 13, 2016 Reconnaissance Survey Meeting 2  
  1. Email re Reconnaissance Survey Meeting 2
  2. Meeting Summary
  3. Comments Crosswalk 
September 22, 2016 Reconnaissance Survey Meeting 3  

Continuation of meeting held on September 13, 2016, and responses to taskers/questions asked during that meeting.

  1. Agenda
October 4, 2016 Reconnaissance Study Boynton Beach, FL

The purpose of the meeting was to continue discussion and resolve issues surrounding the Port Everglades Reconnaissance Study.

  1. Agenda
  2. Meeting Notes
  3. Presentation 
November 3, 2016    
  1. Presentation - 3D Mapping of Reefs
  2. Presentation - the Use and Value of 2D Mosaics in Reef Ecosystems
December 7, 2016    

Schedule update * Update on PED Budget and Use of Available Contingency * Status of revised cost proposals for Recon and ESA Studies * • Memorializing IWG Decisions/Recommendations * Proposed topics for January Orlando meeting

  1. Agenda