The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2018-01972 (SP-MRE)

Published Aug. 9, 2018
Expiration date: 8/30/2018
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below:

APPLICANT:  United Parcel Service, Inc. (UPS)
                       35 Glenlake Parkway NE, Suite 100
                       Atlanta, Georgia 30328

WATERWAY AND LOCATION: The project would affect waters of the United States (wetlands) associated with Cowan Swamp. The project site is located at 2855 Industry Center Road in Section 9, Township 7 South, Range 29 East, St. Augustine, St. Johns County, Florida.

APPROXIMATE CENTRAL COORDINATES:  Latitude 29.910053
                                                                          Longitude -81.385400

PROJECT PURPOSE:

Basic: The basic project purpose is commercial development.

Overall: The overall project purpose is the expansion of a commercial warehouse/distribution facility.

EXISTING CONDITIONS: The project site is approximately 6 acres in total size and encompasses a UPS warehouse/distribution facility, with associated parking and stormwater retention features. The approximate western third of the property is undeveloped and supports a forested wetland system, which extends off-site.

PROPOSED WORK: The applicant seeks authorization to discharge clean fill over a total of 1.73 acres of wetlands to expand the existing facility.

AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment: The work proposed would expand an existing facility. The applicant indicates that relocating the existing facility to another site that would accommodate a larger facility is not economically practical. The proposed facility is expected to accommodate the minimum projected needs of the applicant (i.e., the applicant needs to expand the facility to the proposed size). The applicant also indicates that the proposed facility must meet specific infrastructure requirements (e.g., driveway turn radii for trucks, parking, and size of stormwater treatment ponds), which preclude any reduction to the proposed work area.

COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment: The applicant’s ecological agent submitted a Uniform Mitigation Assessment Method (UMAM) quantifying and qualifying the work affecting wetlands. The UMAM indicates that the work proposed would result in the loss of 1.1 functional units. In consideration of the UMAM, the applicant proposes to purchase 1.1 mitigation bank credits from the Fish Tail Swamp Mitigation Bank.

CULTURAL RESOURCES: The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.

ENDANGERED SPECIES:

Wood Stork (Mycteria americana): The project site is located within the core foraging area of the St. Augustine Alligator Farm Wood Stork colony. However, the project would not affect suitable foraging habitat for Wood Storks. In consideration of this information, the Corps utilized the programmatic consultation procedures associated with The Corps of Engineers, Jacksonville District, U.S. Fish and Wildlife Service, Jacksonville Ecological Services Field Office and State of Florida Effect Determination Key for the Wood Stork in Central and North Peninsular Florida, September 2008, to determine potential effects upon this species. Use of this key resulted in the sequence A-B-no effect. The U.S. Fish and Wildlife Service (FWS) previously indicated that they concur with determinations of no effect based on the key for Wood Storks; and, that no additional consultation is necessary.

The Corps executed a Resources At Risk (RAR) report. The RAR did not indicate that the site is utilized by, or contains habitat critical to, any other federally listed threatened or endangered species. The Corps also reviewed geospatial data and other available information. The Corps has not received or discovered any information that the project site is utilized by, or contains habitat critical to, any other federally listed threatened or endangered species.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service (NMFS) on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The project would not affect marine or estuarine habitat or EFH. Our initial determination is that the proposed action would not adversely affect EFH or federally managed fisheries in Cowan Swamp or downstream waters. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the NMFS.
NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. Corps personnel have not yet verified the proposed delineation of wetlands at the project site.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Jacksonville Permits Section, Post Office Box 4970, Jacksonville, Florida 32232 within 21 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Mark R. Evans, in writing at the Jacksonville Permits Section, Post Office Box 4970, Jacksonville, Florida 32232; by electronic mail at mark.r.evans@usace.army.mil; by facsimile transmission at (904)232-1940; or, by telephone at (904)232-2028.

IMPACT ON NATURAL RESOURCES: Coordination with the Environmental Protection Agency (EPA), the FWS, the NMFS, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.