Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2017-01898 (SP-AWP)

Published May 24, 2018
Expiration date: 6/14/2018
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below:

APPLICANT:  Pulte Home Company
                       c/o Mr. Josh Kalin
                       4901 Vineland Road, Suite 500
                       Orlando, Florida 32811

WATERWAY AND LOCATION: The 711± acre Del Webb - Sunbridge Residential Development project would affect waters of the United States associated with the Kissimmee River Hydrologic Unit (Hydrologic Unit Code 03090101); project is located southeast of Lake Mary Jane. The project site is located south of the Orange-Osceola County Line and east of Narcoosee Road, within Sections 11 & 14, Township 25 South, Range 31 East, in Osceola County, Florida.

Directions to the site are as follows: From Orlando proceed east on State Road (SR) 528 to SR 417 South. Proceed South on SR 417 to Narcoossee Road. Take Narcoossee Road south to Cyrils Drive. Proceed east for 1.8 miles on Cyrils Drive. The gate providing access is located at the intersection of Cyrils Drive and Absher
Road.

APPROXIMATE CENTRAL COORDINATES:  Latitude 28.3215º
                                                                          Longitude -81.1885º

PROJECT PURPOSE:

Basic: Residential Development

Overall: The overall project purpose is for residential development within the Sunbridge at Northeast District (NED) Phase I in Osceola County, Florida.

EXISTING CONDITIONS: The project site currently supports six (6) land use types/vegetative communities. These land use types/vegetative communities were identified utilizing the Florida Land Use, Cover and Forms Classification System, Level III (FLUCFCS, FDOT, January 2004) (Figure 5). The on-site upland land use types/vegetative communities are classified as Pine Flatwoods (411) and Xeric Oak (421). The on-site wetland/surface water land use types/vegetative communities are classified as Streams and Waterways (510), Cypress (621), Wetland Forested Mixed (630), and Freshwater Marshes (641).

PROPOSED WORK: The applicant seeks authorization to dredge and fill 15.12 acres of waters of the United States for construction of residential development.

AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment: With respect to the project’s 15.12 acres of direct wetland impacts to Corps jurisdictional wetlands/surface waters, these impacts account for only 6.7% of the projects total Corps jurisdictional wetlands and/or other surface waters (225.12 acres). Approximately 38% (2.43 acres) of the proposed impacts to W-1 are associated with wetland crossings to access otherwise developable uplands. As indicated on the submitted construction plans, these impacts have been designed such that they are located over the existing/historic wetland crossings (fill roads) in order to further minimize direct impacts. The remaining 3.94 acres of impact are associated with the rear of lots along the project’s eastern limits. Elimination of these impacts would require a reduction of 32 residential lots. It should be stated that none of these impacts constitute 100% lot impacts.

Due to the geometry and location of W-4 and W-13, it was not possible to avoid impacts to these systems. Furthermore, due to the relatively small size of these systems, it is believed that their post-development viability would be significantly reduced once surrounded by development.

COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment: The purchase of federal mitigation credits from an approved mitigation bank.

CULTURAL RESOURCES: The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.

ENDANGERED SPECIES: The action area includes the entire 711± acre project site. The Corps has determined the proposed project “may affect, but is not likely to adversely affect” (NLAA) wood stork (Mycteria americana). The proposed activity is within the Core Foraging Area (CFA) of one rookery; the project supports marginally Suitable Foraging Habitat (SFH) for wood stork. Based on the Effect Determination Key for the Wood Stork in South Peninsular Florida (dated May 2010), the Corps determination sequence is as follows: A (Project impacts SFH at a location greater than 0.47 miles from a colony site) > B (Project impact to SFH is greater in scope than 0.5 acres) > C (Project impacts to SFH within the CFA of a colony site) > E (Project provides SFH compensation) = NLAA. The project provides SFH compensation within the CFA consisting of enhancement, restoration or creation (and federal mitigation bank credits) that provides an amount of habitat and foraging function equivalent to that of the impacted SFH; in accordance with the Clean Water Act section 404(b)(1) guidelines, and is not contrary to the habitat management guidelines. The Corps has U.S. Fish and Wildlife Service (USFWS) concurrence for the proposed activities through use of the aforementioned determination key.

The Corps has determined the proposed project “may affect” the Eastern Indigo Snake (Drymarchon couperi). Based on the Eastern Indigo Snake Programmatic Effect Determination Key (dated August 1, 2017), the Corps determination sequence is as follows: A (The project is not located in open water or salt marsh.) > B (The permit will be conditioned for use of the Service’s Standard Protection Measures for the Eastern Indigo Snake during site preparation and construction.) > C (The project will impact more than 25 acres of eastern indigo snake habitat.) = may affect. The Corps will initiate formal consultation with USFWS pursuant to the aforementioned determination key.

Based on existing habitat types and/or provided survey information, the Corps preliminarily determined the project will have no effect on bluetail mole skink (Eumeces egregious lividus) and sand skink (Neoseps reynoldsi), red-cockaded woodpecker (Leuconotopicus borealis), Everglades Snail Kite (Rostrhamus sociabilis plumbeus), Audubon’s crested caracara (Polyborus plancus audubonii), and Florida scrub-jay (Aphelocoma coerulescens).

ESSENTIAL FISH HABITAT (EFH): The proposed work would have no effect to EFH.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Cocoa Permits Section, 400 High Point Drive, Suite 600, Cocoa, Florida 32926 within 21 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Andrew Phillips, in writing at the Cocoa Permits Section, 400 High Point Drive, Suite 600, Cocoa, Florida, 32926; by electronic mail at andrew.w.phillips@usace.army.mil; by fax at (321) 504-3803, or by telephone at (321) 504-3771 extension 14.

IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The Corps is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.