US Army Corps of Engineers
Jacksonville District Website Website

San Juan Harbor Improvement Study, PR (I)

March 2019

FACT SHEET

San Juan Harbor Improvement Study, PR (I)
Investigation (I)
Congressional District: Puerto Rico

1. DESCRIPTION

San Juan Harbor is located in the north coast of Puerto Pico and is the Island’s principal port. The majority of the commonwealth’s waterborne cargo and cruise ships pass through San Juan Harbor. The harbor currently suffers from shipping inefficiencies due to limited channel width and safety restrictions which do not allow for two-way traffic. Certain sizes of container and cargo vessels cannot exit the port through the Graving Dock area due to limited depth and width and have to turn and transit by the Army Terminal creating delays with incoming ships using the same channels. Cruise ship docking has also reached its full capacity.

2. FUNDING

Estimated Total Cost $3,000,000
Estimated Federal Cost $2,000,000
Allocation thru FY18 $2,130,000
Allocation for FY19 $270,000
President’s Budget FY19 $0

 

3. SPONSOR

Puerto Rico Ports Authority
P.O. Box 362829
San Juan, Puerto Rico 00936-2829

4. STATUS

The Feasibility Cost Sharing Agreement (FCSA) was executed on 16 Sep 2015. The Chief’s Report was completed on 18 Sep 2018. A Design Agreement is scheduled to be executed in April 2019. P&S was initiated. Geotechnical and benthic surveys are scheduled to be awarded in September 2019.

Full-Size Map