U.S. Army Corps of Engineers denies permit for proposed SunWest County Park

Published May 10, 2013

JACKSONVILLE, Fla. – The U.S. Army Corps of Engineers, Jacksonville District has denied a Department of the Army permit application, requested by the Pasco County Board of County Commissioners, to construct a county park with boat access to the Gulf of Mexico. If constructed, the proposed project, called SunWest County Park, would have impacted nearly four acres of jurisdictional wetlands and nearly 29 acres of seagrass habitat.

Under Section 404 of the Clean Water Act of 1972, the Corps regulates the discharge of dredge and fill material in waters of the United States, including many wetlands. Under the Rivers and Harbors Act of 1899, the Corps is responsible for the protection and maintenance of the nation’s navigable waterways. In making its decision, the Corps considers the value of the aquatic ecosystems involved, the views of federal, state and local agencies and interest groups and 21 public interest factors.   

In accordance with the Clean Water Act, the permit applicant must demonstrate that there are no practicable alternatives that would be less damaging to the aquatic environment than the preferred alternative. The Corps determined that the applicant failed to clearly demonstrate that the preferred alternative met this criterion. Additionally, the Corps determined that the proposed project is contrary to the public interest based on several factors, including conservation, economics, general environmental concerns, wetlands, fish and wildlife values, flood hazards, navigation, recreation, water quality and safety.

In response to three public notices relative to the proposed project since 2008, approximately 9,000 individual petition e-mails and two group petition e-mails consisting of approximately 40,000 signatures requested denial of the project. The National Marine Fisheries Service, Center for Biological Diversity, Gulf Coast Conservancy, Save the Manatee Club, Sierra Club of Florida, Florida Wildlife Federation and Gulf Restoration Network all submitted comments expressing opposition to the proposed project.   

“The mission of the U.S. Army Corps of Engineers’ Regulatory program is to protect the nation’s aquatic resources, while allowing reasonable development through fair, flexible and balanced permit decisions,” said Kevin O’Kane, chief of the Tampa Regulatory Office. “We are confident that our decision is based on sound science and a comprehensive, thorough review of potential impacts, including cumulative impacts, of the proposed project on the public’s interest.”

To view the denial letter and the Environmental Assessment/Statement of Findings, please click here:

Sunwest Permit Denial  

# # #


Contact
Nancy J. Sticht
904-232-1667
nancy.j.sticht@usace.army.mil