TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below.
APPLICANT: Angel Nunez
WATERWAY AND LOCATION: The project would affect aquatic resources associated with Florida Bay. The project site is located on an undeveloped lot at 5 Stillwright Way, in Section 01, Township 61 South, Range 39 East, Key Largo, Monroe County, Florida. RE#00514510-000000.
Directions to the site are as follows: Take U.S. 1 south to Key Largo; turn right onto North Blackwater Lane; turn right onto Stillwright Way; Project located to the north of 3 Stillwright Way.
APPROXIMATE CENTRAL COORDINATES: Latitude 25.1596°
Longitude -80.3906°
PROJECT PURPOSE:
Basic: Residential development.
Overall: To construct a single-family residence in Key Largo, Monroe County, Florida.
EXISTING CONDITIONS: The wetland system consists of a saltwater system. The subject property is vacant and located within a subdivision where most platted lots are
developed with single-family residences. This lot supports disturbed saltmarsh consisting of a few green buttonwood trees and wetland groundcover species. The shoreline of the property is occupied by a fringe of mixed-species mangroves but primarily is dominated by Red Mangroves. Wetland vegetation, soil conditions, and hydrological indicators were documented during the field inspection.
PROPOSED WORK: The applicant seeks authorization to place 648 cubic yards of fill within a 7,000 square foot wetland area for the construction of a single-family residence and appurtenant structures.
AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment: The applicant proposes to avoid a portion of the wetland shoreline. Silt fencing and erosion control measures will be deployed to isolate the construction site from adjacent wetlands.
COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment: If mitigation is required by the Army Corps of Engineers the appropriate mitigation will be determined with a UMAM and payment made to Keys Restoration Fund.
CULTURAL RESOURCES: The Corps is aware of recorded historic resources within or adjacent to the permit area and is evaluating the undertaking for effects to historic properties as required under Section 106 of the National Historic Preservation Act. This public notice serves to inform the public of the proposed undertaking and invites comments including those from local, State, and Federal government Agencies with respect to historic resources. Our final determination relative to historic resource impacts may be subject to additional coordination with the State Historic Preservation Officer, those federally recognized tribes with concerns in Florida and the Permit Area, and other interested parties.
ENDANGERED SPECIES:
West Indian Manatee (Trichechus manatus): Potential impacts to the endangered West Indian manatee were evaluated using Corps of Engineers, Jacksonville District, and the State of Florida Effect Determination Key for the Manatee in Florida, April 2013 (Key). Use of the Key resulted in the sequence A (1), “no effect”, where no further consultation with the Service is necessary. This determination is based on no in-water work proposed. Pursuant to Section 7 of the Endangered Species Act, no further consultation with the Service is required.
American crocodile (Crocodylus acutus): The project is located within American crocodile (Crocodylus acutus) the designated critical habitat area. According to the 28 October 2014 American Crocodile Key, the property does not support suitable nesting habitat for the crocodile as the shoreline is heavily vegetated. Use of the Key resulted in the sequence #2 may affect, not likely to adversely affect. Therefore, the Corps has reached a “may affect not likely to adversely affect” determination on the American crocodile and its suitable nesting habitat.
The Corps has determined the proposal would have no effect on any Protected Resource Division (PRD) listed threatened or endangered species or designated critical habitat.
ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The proposal would fill approximately 7,000 square feet (0.16 acres) of disturbed salt marsh wetlands. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries in the Florida Keys. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service.
Navigation: The proposed structure is not located in the vicinity of a federal navigation channel.
SECTION 408: The applicant will not require permission under Section 14 of the Rivers and Harbors Act (33 USC 408) because the activity, in whole or in part, would not alter, occupy, or use a Corps Civil Works project.
NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has been verified by Corps personnel.
COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Florida Keys Permits Section, 9900 Southwest 107th Avenue, Suite 203, Miami, Florida, 33176 within 21 days from the date of this notice.
The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.
QUESTIONS concerning this application should be directed to the project manager, Maria Bezanilla, in writing at the Florida Keys Permits Section, 9900 Southwest 107th Avenue, Suite 203, Miami, Florida, 33176; by electronic mail at Maria.I.Bezanilla@usace.army.mil or by telephone at (786) 795-1976.
IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.
EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people.
Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972.
The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.
WATER QUALITY CERTIFICATION: Water Quality Certification may be required from the Florida Department of Environmental Protection (FDEP). The project is being reviewed under FDEP application no. 44-0296496-006-EI.
COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.
REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.
CLICK HERE FOR PUBLIC NOTICE AND GRAPHICS