Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-1994-04596 (IP-SJF)

U.S. ARMY CORPS OF ENGINEERS - REGULATORY
Published May 17, 2021
Expiration date: 6/7/2021
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:

APPLICANT: Gulf Star Marina
c/o James Carroll
12734 Kenwood Lane, Suite 35
Fort Myers Beach, Florida 33931

WATERWAY AND LOCATION: The project would affect waters of the United States, associated with Mantanzas Pass, adjacent to Estero Bay. The project site is located at 704-724 Fisherman’s Wharf, in Section 24, Township 46 South, Range 23 East, Fort Myers Beach, Lee County, Florida 33931 (Parcel ID: 24-46-23-01-00008.0020).

Directions to the site are as follows: On I-75, take exit 131. Travel west on Daniels Parkway for 2.5 miles. Turn left on 6 Mile Cypress Parkway and travel 3 miles. Continue on Gladiolus Drive for 1.5 miles. Use the left lane to merge on to County Road 869/Summerlin Road via the ramp and continue for 4 miles. Turn left onto Pine Ridge Road then turn left onto San Carlos Boulevard and travel 2.5 miles. Follow around under the bridge onto Fisherman’s Wharf and the site is located on the right.

APPROXIMATE CENTRAL COORDINATES:
Latitude: 26.45909°
Longitude: -81.95249°

PROJECT PURPOSE:
Basic: Reconfigure a commercial docking facility.
Overall: Reconfigure a commercial docking facility, in Fort Myers Beach, Lee County, Florida.

EXISTING CONDITIONS: The existing facility is a working marina with existing docks and dry storage facility. The existing facility has 44 authorized wet slips. The shoreline consists of an existing concrete seawall with rip-rap. The bottom substrate is barren, consisting of fine-sand and silt-clay. No submerged aquatic vegetation or wetlands were observed in the area of the proposed dock, boardwalk and platforms.

PROPOSED WORK: The Applicant seeks authorization to renovate an existing authorized commercial marina. The proposed work involves the removal of 4,167 square feet of existing dock structure and the installation of 6,325 square feet of floating and fixed dock structures, for a total of 9,992 square feet of over water structure. The project will consist primarily of floating docks with 200 square feet of fixed dock structure and one (1) 100 square foot access gangway. The number of wet slips will remain at 44.

CULTURAL RESOURCES: The Corps has determined that the permit area has been extensively modified by previous work and there is little likelihood that an historic property may be affected.

ENDANGERED SPECIES: The Corps made determinations on the following species: West Indian manatee (Trichechus manatus), Green sea turtle (Chelonia mydas), Kemp’s ridley sea turtle (Lepidochelys kempii), Loggerhead sea turtle (Caretta caretta), Smalltooth sawfish (Pristis pectinata).

Basis for determination(s):

West Indian manatee: The project site is located in an Important Manatee (Trichechus manatus) area. The Corps has made the determination that the proposed project may affect, but is not likely to adversely affect (MANLAA), the West Indian manatee and its designated critical habitat. Since the proposal by the applicant is for in-water construction, potential impacts to the endangered manatee were evaluated using The Corps of Engineers, Jacksonville District, and the State of Florida Effect Determination Key for the Manatee in Florida (Manatee Key), dated April 2013. Use of the Manatee Key resulted in the following sequential determination: A>B>C>D>G>N>O>P>3, with further consultation necessary for MANLAA. The Corps will request Fish and Wildlife Service concurrence with this determination pursuant to Section 7 of the Endangered Species Act.

Smalltooth sawfish and sea turtles: The Corps evaluated the proposed work utilizing NMFS’s Jacksonville District’s Programmatic Biological Opinion (JAXBO) dated 20 November 2017. The JAXBO analyzes the effects from 10 categories of minor in-water activities occurring in Florida and the U.S. Caribbean on sea turtles (loggerhead, leatherback, Kemp's ridley, hawksbill, and green); smalltooth sawfish; Nassau grouper; scalloped hammerhead shark, Johnson's seagrass; sturgeon (Gulf, shortnose, and Atlantic); corals (elkhorn, staghorn, boulder star, mountainous star, lobed star, rough cactus, and pillar); whales (North Atlantic right whale, sei, blue, fin, and sperm); and designated critical habitat for Johnson's seagrass; smalltooth sawfish; sturgeon (Gulf and Atlantic); sea turtles (green, hawksbill, leatherback, loggerhead); North Atlantic right whale; and elkhorn and staghorn corals in accordance with Section 7 of the Endangered Species Act. Based on past permitting practices of the Corps and review of consultations with similar in-water construction activities, Project Design Criteria (PDCs) were identified in the JAXBO that typically have been applied to permitted in-water construction activities. These PDCs ensure effects of in-water construction activities are minimal in nature and do not result in adverse effects to listed species or to essential features of designated CH. For this verification, the Corps conducted a project specific review to ensure that all of the PDCs were met. In accordance with the project-specific review process established in the JAXBO, a PDC checklist, certification that the activity meets the applicable PDCs, and supporting documentation for the proposed activity were emailed to nmfs.ser.statewideprogrammatic@noaa.gov and jaxbo@usace.army.mil on 11 May 2021 for Activity 2: Pile Supported Structure. Therefore, the Jacksonville District satisfied the project-specific review requirements stipulated in the JAXBO and satisfied its obligation under the ESA for the above-listed species and critical habitats within the NMFS purview. By programmatic concurrence, no further consultation is required.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The proposal would impact approximately 56 square feet of estuarine or marine habitat utilized by various life stages of Penaeid Shrimp Complex, Red Drum (Sciaenops ocellatus), Reef fish (various spp.), Stone Crab (Menippe mercenaria), Spiny Lobster (Panulirus argus), Migratory/Pelagic fish (various spp.), Snapper/Grouper Complex. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries in the Estero Bay. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service.

NAVIGATION: Based on the Florida State Plane coordinates provided by the applicant, the waterward edge of the proposed structure encroaches to within the absolute minimum distance from the near bottom edge of the Federal Channel.

SECTION 408: The applicant will require permission under Section 14 of the Rivers and Harbors Act (33 USC 408) because the activity, in whole or in part, would alter, occupy, or use a Corps Civil Works project.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has not been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Fort Myers Permits Section, 1520 Royal Palm Square Blvd. Suite 310, Fort Myers, Florida within 21 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Stephen Fleming, in writing at the Fort Myers Permits Section, 1520 Royal Palm Square Blvd. Suite 310, Fort Myers, FL 33919; by electronic mail at Stephen.J.Fleming@usace.army.mil; by facsimile transmission at (239) 334-0797; or, by telephone at 239-334-1975 x0003.

IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, aesthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.