Effective immediately: public notices are published with only the vicinity map, plan view and cross-section drawing. If you are interested in receiving additional project drawings associated with any public notice, please send an email to the project manager at the email address listed in the public notice.

 

Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2001-00881 (SP-MMB)

Published May 5, 2020
Expiration date: 6/5/2020
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:

APPLICANT:
Town of Fort Myers Beach
C/o Chelsea O’Riley
2525 Estero Boulevard
Fort Myers Beach, Florida 33931

WATERWAY AND LOCATION: The project would affect waters of the United States associated with Matanzas Pass, located west of the San Carlos Boulevard Sky Bridge, in Section 13, Township 46 South, Range 23 East, Fort Myers Beach, Lee County, Florida.

Directions to the site are as follows: From Interstate 75, take exit 131 towards Cape Coral/SW Florida International Airport. Travel west on Daniels Parkway for approximately 2.5 miles. Turn left onto 6 Mile Cypress Parkway and travel approximately 3 miles. Continue onto Gladiolus Drive and merge onto County Road 869/Summerlin Road via the ramp to Ft Myers Beach/Sanibel/Captiva and travel approximately 4 miles. Turn left onto Pine Ridge Road. Turn left on FL-865/San Carlos Boulevard and travel for approximately 3 miles until FL-865 becomes Estero Boulevard. Tum left onto Crescent Street and travel approximately 0.3 miles. The project will be on your right under the FL-865 bridge.

APPROXIMATE CENTRAL COORDINATES:
Latitude: 26.460447°
Longitude: -81.960792°

PROJECT PURPOSE:
Basic: Mooring field expansion
Overall: Expansion of the existing Matanzas Harbor Mooring Field along Matanzas Pass, Fort Myers Beach, Florida.

EXISTING CONDITIONS: The existing Matanzas Pass Mooring Field is a 70-slip commercial facility managed by the Town of Fort Myers Beach for recreational vessels up to 58 feet in length. The expansion would include nineteen (19) additional moorings along Matanzas Pass, at least 100 feet from the near bottom edge of the federal channel (Fort Myers Beach Harbor Channel).

PROJECT HISTORY: The Matanzas Harbor Mooring Field is a 70-slip public facility managed by the Town of Fort Myers Beach (Town) for recreational vessels up to 58 feet in length. The existing facility is located within Matanzas Pass, east of the San Carlos Boulevard Sky Bridge (SR-865). The project was permitted by the U.S. Army Corps of Engineers, Permit No. SAJ-2001-00881 on July 15, 2003.

PROPOSED WORK: The Town seeks to expand their mooring field capacity with the addition of the Matanzas Pass Mooring Field, located west of the San Carlos Boulevard Sky Bridge. Nineteen (19) moorings would be added to accommodate vessels up to 80 feet in length. Currently, this area is used as an unregulated mooring field. Four (4) Shallow Shoal markers and two (2) Matanzas Pass Mooring Area markers will be installed in accordance with Florida Fish and Wildlife Conservation Commission requirements. The Town will operate and maintain the Matanzas Pass Mooring Field in accordance with the existing Town of Fort Myers Beach Municipal Anchorage Matanzas Harbor Management Plan dated May 24, 2017.

AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment: “Work will be conducted in a manner that does not cause violations of state water quality standards. Best management practices will be implemented for erosion and pollution control to prevent violations of state water quality standards. The applicant will adhere to current Standard Manatee, Marine Turtle, and Smalltooth sawfish construction conditions for in-water work. See Attachment 3 Best Management Practices.”

COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment: No mitigation is proposed. Work will be conducted in a manner that does not cause violations of state water quality standards. Best management practices will be implemented for erosion and pollution control.

CULTURAL RESOURCES: The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.

ENDANGERED SPECIES: The Corps evaluated the proposed work utilizing the National Marine Fisheries Service (NMFS’s) Jacksonville District’s Programmatic Biological Opinion (JAXBO) dated November 20, 2017. The Corps has determined the proposed project “may affect, not likely to adversely affect” the Green sea turtle (Chelonia mydas), Loggerhead sea turtle (Caretta caretta), Kemp’s Ridley sea turtle (Lepidochelys kempii), or the Smalltooth Sawfish (Pristis pectinata). The applicant agrees to comply with the “Sea Turtle and Smalltooth Sawfish Conditions” dated March 23, 2006. No further consultation is required.

The Corps has determined that the proposed work may affect the West Indian manatee and its designated critical habitat. The Corps made this determination based on the Corps of Engineers, Jacksonville District, and the State of Florida Effect Determination Key for the Manatee in Florida, April 2013 with May 2019 addendum (Manatee Key). Use of the Manatee Key resulted in the following sequential determination: B>C>D>G>H>I>J>K2. The Corps will formally consult with the United States Fish and Wildlife Service (USFWS) under separate letter, pursuant to Section 7 of the Endangered Species Act.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The project site does not contain EFH; therefore, the Corps has determined that the proposed project would have no effect to EFH.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has not been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Fort Myers Permits Section, 1520 Royal Palm Square Blvd. Suite 310, Fort Myers, FL 33919 within 30 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Michelle L. Bartley, in writing at the Fort Myers Permits Section, 1520 Royal Palm Square Boulevard, Suite 310, Fort Myers, Florida 33919; by electronic mail at Michelle.L.Bartley@usace.army.mil; or, by telephone at (239) 334-1975 ext. 0006.

IMPACT ON NATURAL RESOURCES: Coordination with USFWS, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, aesthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.