Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2018-00633(SP-ACM)

Published June 6, 2018
Expiration date: 6/26/2018

TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below:

APPLICANT: Michael DeBuck
                      3899 Mannix Dr.
                      Suite 409
                      Naples, FL 34114-5414

WATERWAY AND LOCATION: The project would affect waters of the United States associated with Spring Creek which leads into Estero Bay (HUC# 03090204). The project site is located at 24145 Claire Street, Section 15, Township 47S, Range 25E Bonita Springs, Lee County, Florida.

Directions to the site are as follows: Proceed along US-41/Tamiami Tail. Turn East on Strike Lane. Turn left on the 4th left, Claire Street. The project will be on the right.

APPROXIMATE CENTRAL COORDINATES: Latitude 26.388845 º
                                                                         Longitude - 81.795385 º

PROJECT PURPOSE:

Basic: Single Family Home

Overall: Construction of a single family home in south west Bonita Springs.

EXISTING CONDITIONS: The wetland system consists of a forested freshwater system. The onsite vegetation consists of 0.82 ac of pine flatwoods and 1.2 ac of hydric pine flatwoods. The existing area surrounding the project area consists of similar vegetation.

PROPOSED WORK: The applicant seeks authorization to discharge fill in 0.94 acres of freshwater wetlands for the construct a single-family residence on PID 154725B2002001320 (1.25 acres) and PID 154725B2002001790 (1.25 acres). The parcel is combined and totals 2.50 acres in size.

AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment:

The applicant consolidated the structures to include one residence in the center of the newly combined lot, and two guest-homes on either side. A 60’ wide vegetative buffer was added to the north and southern property lines. The resulting wetland impact was reduced by approximately 0.51 acres, and now totals 0.94 acres (.47 acres/lot).

COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment:

The project proposes 0.94 acres of forested wetland loss due to filling activity associated with the single-family residence. UWMAM was used to assess the impact area as well as the resulting loss in wetland functions. Based upon a delta factor of 0.46, the applicant shall purchase 0.43 credits of forested freshwater wetland mitigation from an approved mitigation bank. The final proposed mitigation bank, proposed credits, and assessment method used will depend on the availability of credits prior to the issuance of the permit and will be
described by TEC at that time.

CULTURAL RESOURCES:

The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.

ENDANGERED SPECIES:

The Corps has determined the proposed project may affect, but is not likely to adversely affect the Florida Bonneted Bat (Eumops floridanus), Red-cockaded Woodpecker (Picoides borealis), Wood Stork (Mycteria americana), Eastern Indigo Snake (Drymarchon couperi) or its designated critical habitat. The Corps will request U.S. Fish and Wildlife concurrence with this determination pursuant to Section 7 of the Endangered Species Act.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries because the project is located above mean high water.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has not been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of District Engineer through the 1520 Royal Palm Square, Suite 310, Ft. Myers, Florida 33919 within 21 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Allison C. Murphy, in writing at the Ft. Myers Permits Section, 1520 Royal Palm Square Blvd., Ft. Myers, Florida, 33919; by electronic mail at Allison.C.Murphy@usace.army.mil; by facsimile transmission at (239)334-0797; or, by telephone at (239)334-1975 ext. 0008.

IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.