Miami Beach Renourishment Project 2021-2022

The Miami Beach Renourishment 2021 contract will nourish eroded shoreline along Miami-Dade County in the following locations: 64th Street, 55th Street, 46th Street, and 27th Street. The sand source for the project will be truck hauled to the project location. (Click to enlarge)

 

 

 

Construction Start Date:

Currently there is no specific date to start construction. The Contractor hopes to start construction on 64th street (Click pictures to enlarge and see 64th street area) mid-October. 

(USACE photos)

 

Frequently Asked Questions -Miami Beach Renourishment

Collapse All Expand All

The contract awarded to Continental Heavy Civil Corp was for $40,486,000.00.

The contractor will place 835,000 cubic yards of beach-quality sand from an upland source on approximately 11,400  feet of critically eroded shoreline to widen the beach to approximately 90 feet on various segments along the Miami Beach. This number the 300ft of transitions on some of the segments.

 

This project will nourish eroded shoreline along Miami-Dade County in the following locations: 64th Street, 55th Street, 46th Street, and 27th Street.

The project provides coastal storm risk management, including beach erosion control and hurricane surge protection. Beach renourishment projects protect infrastructure, preserve wildlife, support the economy, and build coastal resiliency.

 

Project updates will be available on the Jacksonville District, U.S. Army Corps of Engineers Facebook page: https://
www.facebook.com/JacksonvilleDistrict/ and on Twitter @JaxStrong @MiamiDadeRER @MiamiDadeCounty 
@MiamiBeachNews

The project is expected to be completed by Spring 2023.

The contractor in conjunction with Miami-Dade County will conduct migratory shorebird and sea turtle monitoring daily, and relocate sea turtle nests if necessary. If there are any sea turtle nests in the construction area, they will be monitored and protected until the hatchlings have emerged from the nest. After daily environmental species monitoring and sea turtle nest relocations have been completed and the area has been cleared for construction, beach work will commence. However, construction operations in the area will cease if sea turtles are present at any time.

Safety is our first priority. Due to safety concerns, some beach access areas will be closed and public access to the beach will be restricted during construction. Because of the extensive construction activities for the next several months, motorists, cyclists, pedestrians and beach goers are asked to use caution along these areas of Miami Beach

The contractor will work Monday through Saturday. Approximate work hours at the access and staging areas, including the delivery of sand, will be 6 a.m. through 11 p.m. Beach work will take place between 7 a.m. or sunrise, whichever is later, through 7 p.m. or sunset. Construction will commence after daily sea turtle and shorebird monitoring is complete and the area is cleared for construction.

Project updates will be available at:  https://www.saj.usace.army.mil/Missions/Civil-Works/Shore-Protection/Dade-County/Miami-Beach-Renourishment-2021/

Miami Beach Renourishment Construction Maps

Sept. 28, 2021 (Click maps to enlarge)

Map showing the 2021 Miami Beach Renourishment Project 27th Street SegmentMap showing the 2021 Miami Beach Renourishment Project 46th Street SegmentMap showing the 2021 Miami Beach Renourishment Project 55th Street SegmentMap showing the 2021 Miami Beach Renourishment Project 64th Street Segment

Dade County Shore Protection Background

Flagler County ShorelineDade County officials requested federal assistance with shore erosion about 50 years ago, and Congress authorized the Corps of Engineers to construct the Dade County Beach Erosion Control and Hurricane Protection Project in 1968.

The Dade County project provided for the placement of beach fill along 9.3-miles of shoreline extending from Bakers Haulover Inlet to Government Cut and along the 1.4-mile length of Haulover Beach Park located immediately north of Bakers Haulover Inlet. The 2.4-mile length of the Sunny Isles segment was added to the project in 1985 under a separate authorization.

All major sand sources offshore of Miami-Dade County have now been exhausted with the completion of the latest nourishment contract in the Bal Harbour area in 2014. The Corps and local and state coastal officials estimate that an additional 3.6 million cubic yards of sand is needed for the remaining federal participation, which is ten years for the Government Cut to Baker’s Haulover Beach Park segment and 23 years for the Sunny Isles segment.

Section 935 of the Water Resources Development Act of 1986 and a Congressional directive from 1999 indicate that the Corps can only use domestic sources of sand for renourishment of this project, unless domestic sources are not available for environmental or economic reasons. To utilize new sand sources, the Corps completed a Limited Reevaluation Report (LRR) and Environmental Assessment (EA) with updated economics to justify potential alternative sand sources for future renourishments.

Public Meeting Oct. 7, 2021

A public meeting is scheduled for Oct. 7, 2021. Please see image for meeting details.