May 2024
FACT SHEET
St. Johns County, FL Coastal Storm Risk Management Project
(Ponte Vedra Beach)
Construction (C)
Congressional District: 5, 6
1. DESCRIPTION
The St. Johns County Coastal Storm Risk Management Feasibility Study (Ponte Vedra Beach) was authorized by the June 21, 2000, resolution adopted by the Committee on Transportation and Infrastructure of the United States House of Representatives (Docket 2646). The study includes activities and tasks required to identify and evaluate alternatives and the preparation of a decision document that recommends a coordinated and implementable solution for coastal stork damages in Ponte Vedra Beach, Florida.
2. FUNDING
Estimated Total Cost |
$3,000,000 |
Estimated Federal Cost |
$1,500,000 |
|
|
a. Regular Civil Works Funds:
Allocation thru FY23 |
$500,000 |
Allocation thru FY24 |
$0 |
President's Budget FY25 |
$0 |
|
|
b. P.L. 117-58: Bi-Partisan Infrastructure Law:
Total Work Plan |
$1,000,000 |
Allocation thru FY23 |
$800,000 |
Allocation for FY24 |
$0 |
3. SPONSOR
St. Johns County Board of Commissioners
2740 Industry Center Road
St. Augustine, Florida 32084
4.STATUS
The recommended plan includes 5.1 miles of beach and dune nourishment in the South Ponte Vedra segment (R-78 to R-103.5). The final design includes a 20-foot dune extension in addition to a 20-foot equilibrated berm width at an elevation of 13 feet NAVD88. The project will beach renourished on 10-year intervals using sand from offshore borrow areas (N-1, N-2 and N-3). Signing of the Chief of Engineers Report is currently tracking for 19 Apr 24.