1. DESCRIPTION

The project includes strategic installation of a water main line in Putnam County (east of the St. Johns River). This project will address the concerns of the Florida Department of Environmental Protection (FDEP) by providing potable water access to residential areas in San Mateo, an unincorporated community in Putnam County. The project consists of the design and construction of approximately 21.5 miles of water main installation.

The project is authorized by Section 5061, Water Resources Development Act (WRDA) of 2007.

2. FUNDING

Estimated Total Cost $40,000,000
Estimated Federal Cost     $30,000,000
   

a. Regular Civil Works Funds:

Allocation thru FY23  $0
Allocation for FY24  $0
President's Budget FY25  $0
   

b. P.L. 117-58: Bi-Partisan Infrastructure Law:

Total Work Plan                $5,000,000
Allocation thru FY23 $5,000,000
Allocation for FY24 $0
   

 

3. SPONSOR

Putnam County, Florida 
2509 Crill Avenue Suite 200 P.O.
Palatka, Fl. 32177

4. STATUS

The reimbursable agreement was executed on April 3, 2023.