May 2023
FACT SHEET
Putnam County Water Supply Modernization
Environmental Infrastructure (EI)
Congressional District: 6
1. DESCRIPTION
The project includes strategic installation of a water main line in Putnam County (east of the St. Johns River). This project will address the concerns of the Florida Department of Environmental Protection (FDEP) by providing potable water access to residential areas in San Mateo: an unincorporated community in Putnam County. The project consists of design and construction of approximately 21.5 miles of watermain installation.
The project is authorized by Section 5061, Water Resources Development Act (WRDA) of 2007.
2. FUNDING
Estimated Total Cost |
$40,000,000 |
Estimated Federal Cost |
$30,000,000 |
|
|
a. Regular Civil Works Funds:
Allocation thru FY22 |
$0 |
Allocation for FY23 |
$0 |
President's Budget FY24 |
$0 |
|
|
b. P.L. 117-58: Bi-Partisan Infrastructure Law:
Total Work Plan |
$5,000,000 |
Estimated Federal Cost |
$5,000,000 |
Allocation thru FY22 |
$5,000,000 |
Allocation for FY23 |
$0 |
|
|
3. SPONSOR
Putnam County, Florida
2509 Crill Avenue Suite 200 P.O.
Palatka, Fl. 32177
4. STATUS
The reimbursable agreement was executed on March 30, 2023.