1. DESCRIPTION

The ocean shoreline of St. Johns County is approximately 42 miles long. The St. Johns County Coastal Storm Risk Management Project includes critically eroded shoreline in South Ponte Vedra Beach and Vilano Beach. Extreme erosion north of the St. Augustine Inlet due to the 2016 and 2017 Hurricane seasons has compounded the need for completion of design and construction. The authorized plan includes placement of sand along 3 miles of shoreline in Vilano Beach and South Ponte Vedra Beach. The plan also calls for 3 renourishments (at 12-year intervals) over the project life. 

 

2. FUNDING

a. P.L. 115-123: Bi-Partisan Budget Act of 2018, Supplemental:

Current Working Estimate   $36,800,000
Allocation thru FY19 $1,568,000
Allocation for FY20 $0
 

3. SPONSOR

St. Johns County Board of Commissioners
2740 Industry Center Road
St. Augustine, Florida 32084

 

4. STATUS

Federal funds for design and initial construction were allocated in the Bipartisan Budget Act of 2018. The plans/specifications are currently scheduled for certification on 10 April 2020, advertisement of the contract 21 April 2020 and award in July 2020. The construction duration from notice to proceed is estimated to be 320 calendar days (approximately June 2021).