St. Augustine Harbor FL (O&M)

May 2020

FACT SHEET

St. Augustine Harbor, FL (O&M)
Operations and Maintenance
Congressional Districts: 4, 6

1. DESCRIPTION

The authorized project consists of a channel 16 feet by 200 feet along the best natural alignment as may exist across the new inlet bar, thence 12 feet deep to the Intracoastal Waterway; a sand-trap groin on north side of the inlet extending seaward from shore of Vilano Beach, and a sand-tight jetty on south side of channel extending seaward from shore of Conch Island parallel to and coextensive with the groin; future landward extension of the groin and jetty; and a channel 10 feet by 100 feet in San Sebastian River from the Intracoastal Waterway to King Street Bridge, with a turning place near the upper end.

2. FUNDING

Allocation for FY20 $0
President’s Budget FY21 $0
 

3. SPONSOR

St. Augustine Port Waterway and Beach District
P.O. Box 298
St. Augustine, Florida 32084

4. STATUS

Nothing significant to report at this time. Annual shoaling surveys continue.