Salud Creek at San German (14)

May 2020

FACT SHEET

Salud Creek at San German (14)
Construction (C)
Congressional District: Puerto Rico

1. DESCRIPTION

Salud Creek runs through the middle of the Portal de San German community in the Municipality of San Germán, Puerto Rico. The construction of the project includes clearing and grubbing of approximately 940 linear feet (LF) of eroded channel embankment, grading and compaction of the cleared ground surface, rehabilitation of two single barrel stormwater outfalls (culverts), full bank height bank armoring through the placement of 840 LF of anchored High Performance Turf Reinforcement Mat and concrete armoring of approximately 100 LF of channel embankment surrounding the culverts, and placement of approximately 4 inches of topsoil and sod or seed on stabilized areas.

2. FUNDING

Estimated Total Cost $180,000
Estimated Federal Cost $180,000

a. Regular Civil Works Funds:

Allocation thru FY19      $180,000

b. P.L. 115-123: Bi-Partisan Budget Act of 2018, Supplemental:

Current Working Estimate $2,070,000
Allocation thru FY19 $2,066,000
Allocation for FY20 $0
 

3. SPONSOR

Mayor
Municipality of San German
Interamerican University
#136 P.O. Box 85
San Germán, Puerto Rico 00683

4. STATUS

On 26 March 2019, the Project Partnership Agreement was executed. The Design and Implementation phase is ongoing with a construction contract awarded on 19 Sep 2019 for $1,018,065.73. Construction is scheduled for completion in fall 2020.

Salud Creek at San German Section 14 Project Map