May 2023
FACT SHEET
Tampa Harbor, FL DMDF
Construction (C)
Congressional Districts: 12, 13, 14, 15, 16
1. DESCRIPTION
There are two active Dredge Material Disposal Facilities (DMDFs) associated with Tampa Harbor. These are 2D and 3D. 2D is used for berthing areas (non-federal material). 3D is used for federal channels. Per the 2012 Dredge Material Management Plan, the dikes at DMDF 3D were raised from their previous elevation of 23 feet to 40 feet to accommodate material through 2030.
2. FUNDING
Estimated Total Cost |
$19,300,000 |
Estimated Federal Cost |
$14,500,000 |
a. Regular Civil Works Funds:
Allocation thru FY22 |
$14,989,000 |
Allocation for FY23 |
$0 |
President's Budget FY24 |
$0 |
3. SPONSOR
Port Tampa Bay
1101 Channelside Drive
Tampa, Florida 33602-3612
4. STATUS
The Dredge Material Management Area Raising Contract was completed in August 2015. This contract raised the dike to 40 feet and provided capacity for dredged material for the next 20 years. The Jacksonville District is currently working to balance and closeout the project.