Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2022-00970-(SP-PRC)

USACE Jacksonville District Regulatory
Published Sept. 14, 2022
Expiration date: 10/6/2022
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:

APPLICANT: Anatnal, Inc. (Old Key Lime House)
300 East Ocean Avenue
Lake Worth, FL 33462
ATTN: Ryan Cordero

WATERWAY AND LOCATION

The project is located in waters of the United States within Lake Worth Lagoon adjacent to 110 South Lake Drive and 300 E Ocean Avenue, in Section 3, Township 45 South Range 43 East, Lake Worth, Palm Beach County, Florida.

Directions to the site are as follows: From 95 North take the West Lantana Rd exit. Turn right onto North Dixie Highway heading south. Turn left onto East Ocean Avenue heading East. The property will be on the right, before crossing over the bridge.

APPROXIMATE CENTRAL COORDINATES:
Latitude: 26.58278151
Longitude: -80.04885903

PROJECT PURPOSE:

Basic: The basic project purpose is to improve shoreline stabilization.

Overall: The overall project purpose is to improve shoreline stabilization at 110 South Lake Drive and 300 E Ocean Avenue, Lake Worth, Palm Beach County.

EXISTING CONDITIONS: The project site consists of a single family home and a commercial restaurant (Old Key Lime House) and parking lot with approximately 367.5 linear feet of armored shoreline.

PROPOSED WORK: The applicant seeks authorization to improve shoreline stabilization for the upland single-family home and restaurant through the:
1. Installation of 367.5 linear feet of vinyl sheet seawall with 2.5’ foot wide concrete cap and 41 batter piles.
a. 195.5 linear feet of the wall will be constructed 10 feet waterward of the existing seawall requiring the backfilling of 3,930 square feet (660 cubic yards) of tidal waters.
b. 172 linear feet of the seawall will be constructed 18 inches waterward of the existing wall.

CULTURAL RESOURCES: The Corps has evaluated the undertaking for effects to historic properties as required under Section 106 of the National Historic Preservation Act and has followed the guidelines of 33 CFR Part 325, Appendix C. Due to the project area having been extensively modified by previous work; historic properties that may have at one time existed within the permit area may be presumed to have been lost unless specific information indicates the presence of such. Hence, the Corps has determined that the project would have No Potential to Cause Effects to Historic Properties.

AVOIDANCE AND MINIMIZATION INFORMATION: The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment:

The proposed bank stabilization has been planned and designed to avoid environmental impacts.

On June 10, 2022, a benthic survey was conducted and no benthic resources were found within the project area. The applicant has agreed to comply with JAXBO PDC’s for In-Water Activities, including the use of turbidity curtains and will comply with the Standard Manatee Conditions for In-Water Work – 2011.

COMPENSATORY MITIGATION: The applicant has provided the following explanation why compensatory mitigation should not be required:

The project will not impact aquatic resources hence mitigation is not required.

ENDANGERED SPECIES: The U. S. Army Corps of Engineers (Corps) has determined the proposed project may affect, but not likely to adversely affect the threatened West Indian manatee (Trichechus manatus) and would not adversely modify its designated critical habitat. Use of The Corps of Engineers, Jacksonville District, and the State of Florida Effect Determination Key for the Manatee in Florida, (the Key) dated April 2013 and May 2019 Addendum, results in the following sequential determination: A-B-C-G-N-O-P, paragraph 1 “may affect, not likely to adversely affect.” Applicant will adhere to the “Manatee construction conditions.” Therefore, no further coordination pursuant to Section 7 of the Endangered Species Act with the U.S. Fish and Wildlife Service is necessary.

The Corps has determined the proposed project may affect, but is not likely to adversely affect the swimming green, Kemp’s Ridley, and loggerhead sea turtles, (Chelonia mydas, Lepidochelys kempii, and Caretta caretta), and the Smalltooth sawfish (Pristis pectinata). The Corps will request National Marine Fisheries Service concurrence with this determination pursuant to Section 7 of the Endangered Species Act by separate correspondence via the Jacksonville District Biological Opinion (JAXBO) supersede process.

The Corps has determined the proposal would have no effect on any other listed threatened or endangered species or designated critical habitat.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act of 1996. The proposal would impact approximately 3,930 square feet the submerged lands, which are utilized by various life stages of penaeid shrimp complex, reef fish, stone crab, spiny lobster, migratory/pelagic fish, and snapper/grouper complex. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries within the South Atlantic Region. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Palm Beach Gardens Regulatory Permits Section, 4400 PGA Boulevard, Suite 500, Palm Beach Gardens, FL 33410, within 21 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated aquatic resources. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Ms. Patricia Clune, in writing at the Palm Beach Gardens Regulatory Permits Section, 4400 PGA Boulevard, Suite 500, Palm Beach Gardens, FL 33410, by electronic mail at Patricia.R.Clune@usace.army.mil, by fax at (561)626-6971, or by telephone at (561) 768-5944.

IMPACT ON NATURAL RESOURCES: Preliminary review of this application indicates that an Environmental Impact Statement will not be required. Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Service, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area. By means of this notice, we are soliciting comments on the potential effects of the project on threatened or endangered species or their habitat.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act and the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment and/or an Environmental Impact Statement pursuant to the National Environmental Policy Act. comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.