Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2020-02376 (SP-MIB)

Published Dec. 7, 2020
Expiration date: 12/29/2020
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) and Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:

APPLICANT: Samuel Rivera
4208 Daubert Street
Orlando, Florida 32803

WATERWAY AND LOCATION: The project would affect waters of the United States associated with the Atlantic Ocean. The project site is located on a vacant lot on Copa D’Oro; legally described as BK 1 Lt 60 Amended Plat of Flamingo Island Estates Boot Key, PB5-121 in Section 15, Township 66 south, Range 32 east; Marathon, Monroe County, Florida (RE#00356040-000000).

Directions to the site are as follows: Take U.S. 1 South to Overseas Highway; Continue on Overseas Hwy South to MM50; Turn left onto Sombrero Beach Road; Turn right onto Sombrero Boulevard; Turn left onto Sombrero Road; Turn left onto the bridge; Turn left onto Copa D’Oro East; Project is located to the north of 839 Copa D’Oro.

APPROXIMATE CENTRAL COORDINATES:

Latitude: 24.702996°
Longitude: -81.083092°

PROJECT PURPOSE:

Basic: To construct a single-family residence with appurtenant structures and to provide boating access.

Overall: To construct a single-family residence and to provide boating access in Marathon, Monroe County, Florida.

EXISTING CONDITIONS: The project is located within a developed subdivision of Marathon adjacent to a canal that flows into the Atlantic Ocean. The property supports a disturbed herbaceous wetland lot with a mature mangrove and buttonwood shoreline. The vegetation on the lot consists of sparse to moderate coverage of primarily of sea purslane intermixed with hurricane grass, coastal drop seed, and buttonwood saplings. The site inspection documented algal matting, marl soil, and standing water. The lot supports wetland vegetation, hydric soils and hydrology.

PROPOSED WORK: The applicant seeks authorization to place 454 cubic yards of fill within a 6,133 square foot jurisdictional wetland area for the construction of a single-family residence with appurtenant structures (i.e. driveway, swale, riprap revetment, etc.), to construct a 320 square foot “T”-shaped dock with a 4 foot wide by 14.3 foot lone access walkway leading to a 5 foot wide by 52.5 foot long terminal platform; to install temporary floating turbidity barriers around all work areas that are in/over U.S. navigable waters, and to avoid the remaining 285 square feet of onsite wetland shoreline.

AVOIDANCE AND MINIMIZATION INFORMATION – The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment: Prior to the start of construction, turbidity curtains will be deployed to isolate the construction site from ambient waters. The applicant proposes to avoid 285 square foot area of onsite wetland shoreline in perpetuity.

COMPENSATORY MITIGATION – The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment: If it is determined that the issuance of a DA permit is appropriate, mitigation will be required. The applicant has indicated that the mitigation proposal will be based on the Keys Restoration Fund (KRF). Time lag and risk will be a required component of any mitigation requirement.

CULTURAL RESOURCES:

The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.

ENDANGERED SPECIES:

The real estate parcel number is 00356040-000000 and is on the U.S. Fish and Wildlife Service Suitable Habitat List, dated August 2010, for Monroe County for the Eastern indigo snake.

The U.S. Army Corps of Engineers (Corps) has determined the project may affect, but is not likely to adversely affect (“MANLAA”) the West Indian manatee (Trichechus manatus) or its designated critical habitat. Since the proposal by the applicant is for in-water construction, potential impacts to the endangered manatee were evaluated using The Corps of Engineers, Jacksonville District, and the State of Florida Effect Determination Key for the Manatee in Florida (Manatee Key), dated April 2013. Use of the Manatee Key resulted in the following sequential determination: A > B > C > G > H > I > N > O > P1 “may affect, but is not likely to adversely affect.” This determination partially was based on the implementation of the Standard Manatee Conditions for In-Water Work. The Corps has concurrence with this determination pursuant to the Effect Determination Key for the manatee dated April 2013.

The project is located within American crocodile (Crocodylus acutus) the designated critical habitat area. According to the 28 October 2014 American Crocodile Key, the property does not support suitable nesting habitat for the crocodile as the shoreline is densely vegetated. Use of the Key resulted in the sequence #2 may affect, not likely to adversely affect. Therefore, the Corps has reached a “may affect not likely to adversely affect” determination on the American crocodile and its suitable nesting habitat.

The Corps has determined the proposed project may affect, but is not likely to adversely affect (“MANLAA”) the swimming green sea turtles (Chelonia mydas), loggerhead sea turtles (Caretta caretta), hawksbill sea turtles (Eretmochelys imbricata), Kemp’s ridley sea turtles (Lepidochelys kempii), leatherback sea turtles (Dermochelys coriacea), the smalltooth sawfish (Pristis pectinata), and Nassau grouper (Epinephelus striatus) species. A no effect determination was reached on Acorpora sp. and its designated critical habitat and corals species; (Dendrogyra cylindrus, Orbicella annularis, Orbicella faveolata, Orbicella franksi, and Mycetophyllia ferox). The Corps will request National Marine Fisheries Service concurrence with this determination pursuant to Section 7 of the Endangered Species Act.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The proposal would impact approximately 6,453 square feet of wetlands and submerged bottom utilized by various life stages of marina species. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries in the Florida Keys. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has not been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Miami Permits Section, 9900 Southwest 107th Avenue, Suite 203, Miami, Florida 33176 within 21 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Maria Bezanilla, in writing at the Miami Permits Section, 9900 Southwest 107th Avenue, Suite 203, Miami, Florida 33176; by electronic mail at Maria.I.Bezanilla@usace.army.mil or by telephone at (305) 779-6057.

IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan. In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board. In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.