Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2019-00294 (SJC)

Published May 29, 2019
Expiration date: 6/27/2019

TO WHOM IT MAY CONCERN:  The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received a complete prospectus proposing the establishment of a mitigation bank pursuant to the 2008 Compensatory Mitigation for Losses of Aquatic Resources regulations (33 CFR Part 332) as described below:

APPLICANT:  Mr. John Cassidy
                       Pigeon Creek Mitigation Bank, LLC
                       4223 Lakeside Drive
                       Jacksonville, Florida 32210

LOCATION: The proposed project, identified as the Pigeon Creek Mitigation Bank (PCMB), is bordered to the north by Bay Road, and to the south by Magnolia Avenue, west of U.S. Highway 1 in Hilliard, Nassau County. The site lies within Section 13, Township 3 North, Range 23 East, and Sections 18 & 19 of Township 3 North, Range 24 East.

APPROXIMATE CENTRAL COORDINATES:  Latitude 30.676394°
                                                                          Longitude -81.949321°

PROSPECTUS SUMMARY: Pursuant to 33 CFR 332.8(d)(4), the Corps has posted a full copy of the PCMB prospectus online so that it is available for review by the public. The prospectus may be downloaded from the Regulatory In-Lieu Fee and Bank Information Tracking System (RIBITS) at web address: https://ribits.usace.army.mil.

Once on the RIBITS homepage, select "Jacksonville" from the "ALL DISTRICTS" drop down menu located in the lower left corner of the screen. Once the district filter has been selected, click on the “Banks & ILF Sites” link located in the Navigation box (upper left corner). This will generate a list of projects, scroll down the list and click on the “Pigeon Creek MB” link. On this page, click on the "Cyber Repository" link located on the menu bar above the General Information box, then click on the Prospectus Documents folder to access the prospectus associated with the PCMB project.

If you are unable to access the web address, a copy of the prospectus is available upon request to the project manager listed at the end of this public notice.

PROJECT GOALS AND OBJECTIVES:

As stated by the applicant, the goals of this mitigation bank are:

• To provide additional, enhanced, and more diverse habitat for resident and migratory wildlife (protected and non-protected species) that are known to occur
  within and around the project area,
• To maximize the ecological value of the site through preservation and enhancement
• To restore natural vegetative and hydrologic conditions in the on-site communities

The objectives of the mitigation bank include, but are not limited to, the following:

• Elimination of silvicultural planting activities and most planted pines
• Elimination of use of herbicide and fertilizer
• Eliminate tree harvesting practices
• Restoration of natural hydrologic flows and hydroperiods currently disrupted by trail roads
• Implementation of mechanical clearing and/or prescribed burning to restore natural communities
• Removal of trail roads built in and around wetlands in several areas to restore natural wetland grades and functions
• Restoration of natural vegetative structural components within disturbed wetland depressions and swamps through pine removal
• Protection from high intensity hunting
• Implementation of conservation easements
• Control of floral and faunal exotic and/or nuisance species

CULTURAL RESOURCES: The proposed bank is not expected to have any direct or indirect impact to cultural resources. Project review will, however, include review of the proposal for any potential impact to cultural resources.

ENDANGERED SPECIES: The site will be reviewed for potential critical habitat and presence of endangered species. The findings will be coordinated with the U.S. Fish and Wildlife service.

ESSENTIAL FISH HABITAT (EFH): It is unlikely that essential fish habitat is present onsite, however, the project proposal will be coordinated with the pertinent federal agencies to minimize the risk for any potential impact to EFH.

NOTE: This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.

COMMENTS: Comments regarding the proposed mitigation bank should be submitted in writing to the District Engineer at the address below within 30 days from the date of this notice.

The initial evaluation pertaining to whether or not this mitigation bank proposal has the potential for providing compensatory mitigation for activities authorized by issued Department of the Army permits will be based on the information contained in the prospectus, received from this public notice and obtained during an inspection of the project site.

If you have any questions concerning this proposed project, you may contact Mr. Steven Currie by electronic mail at steven.j.currie@usace.army.mil, by fax at 904-232-1904, or by telephone at 904-232-3701 or at the following address:

DEPARTMENT OF THE ARMY
JACKSONVILLE DISTRICT CORPS OF ENGINEERS
P. O. BOX 4970
JACKSONVILLE, FLORIDA 32232-0019

IMPACT ON NATURAL RESOURCES: Preliminary review of this application indicates that an Environmental Impact Statement will not be required. Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area. By means of this notice, we are soliciting comments on the potential effects of the project on threatened or endangered species or their habitat

EVALUATION: After the end of the comment period, the district engineer will review all comments received and make an initial determination as to the potential of the proposed project to provide compensatory mitigation for activities authorized by Department of the Army permits. That determination will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. Factors relevant to the proposal will be considered including conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people.

The Corps is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the proposed activity. All comments received will be considered by the Corps during the formulation of the initial determination of potential for the proposed activity.