Effective immediately: public notices are published with only the vicinity map, plan view and cross-section drawing. If you are interested in receiving additional project drawings associated with any public notice, please send an email to the project manager at the email address listed in the public notice.

 

Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2007-06005 (SP-JSC)

Published Dec. 6, 2018
Expiration date: 12/21/2018
TO WHOM IT MAY CONCERN: The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. §1344) as described below:

APPLICANT: JBL Asset Management, LLC
c/o Jacob Khotoveli
20258 Harrison St., Suite 202
Hollywood, Florida 33020

WATERWAY AND LOCATION: The proposed ±20-acre Orlando Gateway project is located north of SR 528 and west of SR 436 in the City of Orlando, Orange County (Section 28, Township 23 South, Range 30 West), Florida. The project would affect waters of the United States associated with the East Lake Tohopekaliga Hydrologic Unit (Hydrologic Unit Code 0309010101).

Directions to the Site: From SR 528, proceed north on SR 436 a quarter mile. The project site will be on the immediate left.

APPROXIMATE CENTRAL COORDINATES:
Latitude: 28.4521○
Longitude: -81.3123○

PROJECT PURPOSE:

Basic: commercial construction

Overall: The overall project purpose is construction of a commercial multi-family subdivision on the existing Orlando Gateway project in Orange County, Florida.

PROJECT DESCRIPTION: The project was previously authorized March 23, 2009 with the permit expiring May 8, 2014, prior to the completion of authorized work. The proposed development plan for this site includes construction of a commercial subdivision, including associated road and stormwater treatment infrastructure.

EXISTING CONDITIONS: The proposed project would result in direct impacts to 8.31 acres of waters of the United States.
On-site aquatic resources include Wetlands C (3.74 acres) and EFD (4.57 acres), which are characterized as Wetland Forested Mixed systems. Wetland Forested Mixed includes red maple, loblolly bay sweetgum and pond pine canopy. All systems are significantly drained by the canal along the southern property boundary. This canal drains surface water and groundwater from these systems. Due to surrounding roads, the canal, and development, the wetland systems have a reduced contributing area for hydrologic support.

PROPOSED WORK: The Applicant seeks reauthorization to place fill in 8.31-acres of waters of the United States for construction of a commercial multi-family subdivision on the existing Orlando Gateway project in Orange County, Florida

AVOIDANCE AND MINIMIZATION INFORMATION: The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment:

“The majority of impacts are to highly degraded and disturbed wetland systems, some of which may be isolated. The mitigation is regionally significant and will provide greater long-term ecological value.”

COMPENSATORY MITIGATION: The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment:

The previous Permittee purchased 6.26 federal palustrine credits from the East Central Florida Regional Mitigation Bank on May 11, 2010. This included compensatory mitigation for the proposed 8.31 acres of wetland fill.

CULTURAL RESOURCES:
The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review. Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and/or Tribes.

ENDANGERED SPECIES: The applicant indicated no federally listed plant species occur on the project site. The Corps has completed preliminary federally listed species affect determinations which include the following:

The proposed activity is within the Core Foraging Area (CFA) of a wood stork (Mycteria americana) rookery; the project supports marginally Suitable Foraging Habitat (SFH) for wood stork. Based on the Effect Determination Key for the Wood Stork in Central and North Peninsular Florida (dated September 2008), the Corps determination sequence was A>B>C>E = “may affect, not likely to adversely affect”. The determination is supported by SFH compensation provided within the service area of a mitigation bank which covers the CFA, and provides an amount of habitat and foraging function equivalent to that of impacted SFH; is not contrary to the Service’s Habitat Management Guidelines For The Wood Stork In The Southeast Region and in accordance with the CWA Section 404(b)(1) guidelines. The Corps has U.S. Fish and Wildlife Service concurrence for the proposed activities through the use of the aforementioned determination key.

The Corps has determined the proposed project “may affect, but is not likely to adversely affect” the Eastern Indigo Snake (Drymarchon corais couperi). Based on the Eastern Indigo Snake Effect Determination Key (dated January 25, 2010; August 13, 2013 Addendum), the Corps determination sequence is as follows: A (The project is not located in open water or salt marsh.) >B (The permit will be conditioned for use of the Service’s Standard Protection Measures for the Eastern Indigo Snake during site preparation and protection construction.) >C (There are gopher tortoise burrows, holes, cavities, or other refugia where a snake could be buried or trapped and injured during project activities.) >D (The project will impact less than 25 acres of xeric habitat supporting less than 25 active and inactive gopher tortoise burrows ) >E (Any permit will be conditioned such that all gopher tortoise burrows, active or inactive, will be evacuated prior to site manipulation in the vicinity of the burrow) = NLAA. The permittee agrees to use the Standard Protection Measures for the Eastern Indigo Snake (dated August 12, 2013). If an indigo snake is encountered, the snake must be allowed to vacate the area prior to additional site manipulation in the vicinity. Any permit will also be conditioned such that holes, cavities, and snake refugia other than gopher tortoise burrows will be inspected each morning before planned site manipulation of a particular area, and, if occupied by an indigo snake, no work will commence until the snake has vacated the vicinity of proposed work. The Corps has U.S. Fish and Wildlife Service concurrence for the proposed activities through the use of the aforementioned determination key.

The project is within the Consultation Area for Bluetail mole skink (Eumeces egregious lividus) and Sand skink (Neoseps reynoldsi), Florida scrub jay (Aphelocoma coerulescens), Everglades snail kite (Rostrhamus sociabilis plumbeus), Aububon’s crested caracara (Polyborus plancus audubonii), and Red-cockaded woodpecker (Picoides boerealis). Based on existing habitat types, the Corps preliminarily determined the project will have no effect on these species.

ESSENTIAL FISH HABITAT (EFH): This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996. The proposal would impact approximately 8.31 acres of freshwater wetlands and surface waters which ultimately discharge to the Kissimmee River. Our initial determination is that the proposed action would not have a substantial adverse impact on downstream EFH or Federally managed fisheries. Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service (NMFS).
NOTE: This public notice is being issued based on information furnished by the applicant.
This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has been verified by Corps personnel.

AUTHORIZATION FROM OTHER AGENCIES: Water Quality Certification will be required from the South Florida Water Management District.

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Cocoa Permits Section, 400 High Point Drive, Suite 600, Cocoa, Florida 32926, within 15 days from the date of this notice.

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands. This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

QUESTIONS concerning this application should be directed to the project manager, Jeffrey S. Collins, in writing at the Cocoa Permits Section (address above), by electronic mail at Jeffrey.s.collins@usace.army.mil, or by telephone at (321) 504-3771.

IMPACT ON NATURAL RESOURCES: Coordination with USFWS, Environmental Protection Agency (EPA), the NMFS, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972. A permit will be granted unless its issuance is found to be contrary to the public interest.

The Corps is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan.

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.