Naples to Big Marco Pass FL (O&M)

June 2021

FACT SHEET

Naples to Big Marco Pass, FL (O&M)
Operations and Maintenance
Congressional Districts: 19, 25

1. DESCRIPTION

The project includes the southerly 10.15 miles of the waterway from Naples to Big Marco Pass and 4.5 miles of waterway from Naples to Gordon Pass. An interior channel 6 x 70 feet from southerly limits of the town of Naples to Big Marco Pass; a channel 12 x 150 feet from that depth in the Gulf to Gordon Pass, thence 10 x 100 feet through Gordon Pass and Naples Bay to a point 400 feet south of the U.S. 41 highway bridge, thence 10 x 70 feet to the bridge; and a turning basin 8 x 150 x 200 feet in upper Naples Bay; and a turning basin 8 x 250 x 670 feet at the municipal yacht basin.

2. FUNDING

a. Regular Civil Works Funds:

Allocation for FY21 $0
President's Budget for FY22 $0

 

b. P.L. 115-123: Bi-Partisan Budget Act of 2018, Supplemental:

Current Working Estimate $400,000
Allocation thru FY20 $400,000
Allocation for FY21 $0

 

3. SPONSOR

City of Naples
735 8th St S
Naples, Florida 34102 

4. STATUS

The Jacksonville District continues to perform project condition surveys of the Federal channel. With class 3 O&M Supplemental (P.L. 115-123) funding, the team performed new surveys for updated volumes and completed the plans and specs for advertisement in March 2020 and contract award on April 21, 2020. Approximately 87,000 cubic yards of material were removed from Cut 1 and the Settling Basin and placed on Keewaydin Island located south of the inlet. Construction activities were completed in August 2020. The Corps is currently evaluating engineering and environmental requirements for a northern beach placement as an option to the southerly beach placement.

 

Naples to Big Marco Pass Operations and Maintenance project map