Public Notice Notifications

The Jacksonville District currently has five categories of public notice notification mailing lists. If you wish to receive email notifications when new public notices are added to this page, please send a request to Regulatory Webmaster.  Each category is described below. Be sure to specify which list(s) you want to be included on.

Florida - This includes all public notices for projects being reviewed for Standard Permits within the State of Florida.

Antilles - This includes all public notices for projects being reviewed for Standard Permits within the Antilles area (this includes Puerto Rico and the US Virgin Islands).

Tropical Storms & Other Emergencies - These public notices provide information on procedures for emergency permitting requirements due to specific tropical storm events or other emergency situations.

Special Issues - These are public notices that involve the Regulatory program but which are generally not limited to one particular geographic area. These would include public notices for the establishment or modification of Restricted Areas/Danger Zones, re-issuance of General Permits or Nationwide Permits, changes to guidance and policies, etc.

Administrative Penalty - These public notices provide information associated with Administrative Penalties. An Administrative Penalty can be assessed to address violations associated with issued Department of the Army permits.

SAJ-2020-04101(SP-AMC)

Published Dec. 14, 2020
Expiration date: 1/4/2021

 

TO WHOM IT MAY CONCERN:  The Jacksonville District of the U.S. Army Corps of Engineers (Corps) has received an application for a Department of the Army permit pursuant to Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. §403) as described below:

 

APPLICANT:  Frank Diaz

                       11301 NW 62nd Ct

                       Hialeah, Florida 33012

 

WATERWAY AND LOCATION:  The project would affect waters of the United States associated with canal system within the Gulf of Mexico.  The project site is located at 65821 Overseas HWY #93; legally described as LT 93 Property Line Survey Section 1 Long Key Project in Section 7, Township 65 South, Range 35 East, Long Key, Monroe County, Florida 33001. (MM± 65).

 

Directions to the site are as follows:  From Miami, drive south on U.S. 1, Overseas Highway, turn right onto Pelican Court, turn right at the first cross street, turn right at Grouper Ct, then turn left.    

 

APPROXIMATE CENTRAL COORDINATES:    Latitude:       24.804700° North

                                                                            Longitude:   -80.847524° West

 

PROJECT PURPOSE:

Basic:  The basic project purpose is to remove the vessel from the water when not in use..

Overall: The overall project purpose is to remove the vessel from the water when not in use, in Long Key, Monroe County, Florida.

 

EXISTING CONDITIONS:  The site has an existing concrete retaining wall/dock with stairs leading to the water.  There are not corals, seagrass and mangroves on site,

 

PROPOSED WORK:  The applicant seeks authorization to install a 10,000lb boat lift,12 feet long by 10 feet side (3 pages). Temporary turbidity curtains will be deployed for the duration of all construction activities, in/over waters of the United States.

 

AVOIDANCE AND MINIMIZATION INFORMATION: The applicant has provided the following information in support of efforts to avoid and/or minimize impacts to the    aquatic environment:

Prior to the start of construction, turbidity curtains will be deployed for in water work.

The applicant agrees to comply with the "Standard Manatee Conditions for In-Water Work – 2011" the "Sea Turtle and Smalltooth Sawfish Construction Conditions."

 

COMPENSATORY MITIGATION: The applicant has offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment:

If mitigation is required by the ACOE, appropriate mitigation will be determined with a UMAM and payment will be made to the Keys Restoration Fund.

 

CULTURAL RESOURCES:  The Corps is not aware of any known historic properties within the permit area. By copy of this public notice, the Corps is providing information for review.  Our final determination relative to historic resource impacts is subject to review by and coordination with the State Historic Preservation Officer and those federally recognized tribes with concerns in Florida and the Permit Area.

 

ENDANGERED SPECIES:   The U.S. Army Corps of Engineers (Corps) has determined the project may affect, but is not likely to adversely affect (“MANLAA”) the West Indian manatee (Trichechus manatus).  Since the proposal by the applicant is for in-water construction, potential impacts to the endangered West Indian manatee were evaluated using The Corps of Engineers, Jacksonville District, and the State of Florida Effect Determination Key for the Manatee in Florida, April 2013 (Key).  Use of the Key resulted in the following sequential determination:  B > C > G > H>I>N > 0 > P (4), may affect, not likely to adversely affect “MANLAA”.  This determination is partially based on the implementation of the Standard Manatee Conditions for In-Water Work, 2011.  By letter dated April 25, 2013, the Corps received concurrence from the U.S. Fish and Wildlife Service (FWS) regarding MANLAA determinations for the West Indian manatee in accordance with 50 CFR 402.14(b)1 and pursuant to the Key.  No further coordination with the FWS is required.

The U.S. Army Corps of Engineers (Corps) has determined the project may affect, but is not likely to adversely affect (“MANLAA”) the American crocodile (Crocodylus acutus).

The project is located within American crocodile (Crocodylus acutus) consultation area.  According to the 28 October 2014 American Crocodile Key, the property does not support suitable nesting habitat for the crocodile. Use of the Key resulted in the sequence #2B may affect, not likely to adversely affect. Therefore, the Corps has reached a “may affect not likely to adversely affect” determination on the American crocodile and its suitable nesting habitat.

The Corps has determined that the project will have “no effect” on the Piping plover (Charadrius melodus) and roseate tern (Sterna dougallii). The proposed work is located outside of native habitat for these species. No impact to native /natural habitat is included

The Corps has determined the proposed project may affect, but is not likely to adversely affect (“MANLAA”) the swimming green sea turtles (Chelonia mydas), loggerhead sea turtles (Caretta caretta) and their critical habitat, hawksbill sea turtles (Eretmochelys imbricata), kemps ridley sea turtles (Lepidochelys kempii), leatherback sea turtles (Dermochelys coriacea and Acorpora sp. and its designated critical habitat. A no effect determination was reached on and corals species; (Dendrogyra cylindrus, Orbicella annularis, Orbicella faveolata, Orbicella franksi, Mycetophyllia ferox). The Corps will request National Marine Fisheries Service concurrence with these determinations pursuant to Section 7 of the Endangered Species Act. 

 

ESSENTIAL FISH HABITAT (EFH):  This notice initiates consultation with the National Marine Fisheries Service on EFH as required by the Magnuson-Stevens Fishery Conservation and Management Act 1996.  The proposal would impact approximately 2 square feet of submerged aquatic resources utilized by various life stages of land and marine species. Our initial determination is that the proposed action would not have a substantial adverse impact on EFH or Federally managed fisheries in the Florida Keys.  Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the National Marine Fisheries Service.

 

NOTE:  This public notice is being issued based on information furnished by the applicant. This information has not been verified or evaluated to ensure compliance with laws and regulation governing the regulatory program. The jurisdictional line has not been verified by Corps personnel.

 

AUTHORIZATION FROM OTHER AGENCIES:  Water Quality Certification may be required from the Florida Department of Environmental Protection and/or one of the state Water Management Districts.

 

COMMENTS regarding the potential authorization of the work proposed should be submitted in writing to the attention of the District Engineer through the Miami Permits Section, 9900 Southwest 107th Avenue, Suite 203, Miami, Florida, 33176, within 21 days from the date of this notice (i.e. on or before January 4, 2021).

 

The decision whether to issue or deny this permit application will be based on the information received from this public notice and the evaluation of the probable impact to the associated wetlands.  This is based on an analysis of the applicant's avoidance and minimization efforts for the project, as well as the compensatory mitigation proposed.

 

QUESTIONS concerning this application should be directed to the project manager, Adriana M. Cabrera at the letterhead address, by electronic mail at Adriana.M.Cabrera@usace.army.mil, or by telephone at (305) 526-7173. 

 

IMPACT ON NATURAL RESOURCES: Coordination with U.S. Fish and Wildlife Service, Environmental Protection Agency (EPA), the National Marine Fisheries Services, and other Federal, State, and local agencies, environmental groups, and concerned citizens generally yields pertinent environmental information that is instrumental in determining the impact the proposed action will have on the natural resources of the area.

 

EVALUATION: The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefits, which reasonably may be expected to accrue from the proposal, must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including cumulative impacts thereof; among these are conservation, economics, esthetics, general environmental concerns, wetlands, historical properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food, and fiber production, mineral needs, considerations of property ownership, and in general, the needs and welfare of the people. Evaluation of the impact of the activity on the public interest will also include application of the guidelines promulgated by the Administrator, EPA, under authority of Section 404(b) of the Clean Water Act or the criteria established under authority of Section 102(a) of the Marine Protection Research and Sanctuaries Act of 1972.  A permit will be granted unless its issuance is found to be contrary to the public interest.

 

The US Army Corps of Engineers (Corps) is soliciting comments from the public; Federal, State, and local agencies and officials; Indian Tribes; and other Interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps to determine whether to issue, modify, condition, or deny a permit for this proposal. To make this determination, comments are used to assess impacts to endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above. Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity.

 

COASTAL ZONE MANAGEMENT CONSISTENCY: In Florida, the State approval constitutes compliance with the approved Coastal Zone Management Plan.  In Puerto Rico, a Coastal Zone Management Consistency Concurrence is required from the Puerto Rico Planning Board.  In the Virgin Islands, the Department of Planning and Natural Resources permit constitutes compliance with the Coastal Zone Management Plan.

 

REQUEST FOR PUBLIC HEARING: Any person may request a public hearing. The request must be submitted in writing to the District Engineer within the designated comment period of the notice and must state the specific reasons for requesting the public hearing.