U.S. Marine Corps – Blount Island (O&M)

March 2018


FACT SHEET

U.S. Marine Corps – Blount Island (O&M)

Operations & Maintenance

Congressional Districts: 4

1. DESCRIPTION

The work consists of maintenance dredging the 38-foot slip basin at the U.S. Marine Corps Support Facility Blount Island, Jacksonville, Florida.

2. FUNDING

Allocation for FY18 (USMC) $2,750,000
President’s Budget FY19 $3,000,000

3. SPONSOR

U. S. Marine Corps
Support Facility Blount Island
Jacksonville, FL 32226

4. STATUS

Approximately 125,000 cubic yards is maintenance dredged every year. Dredged material is placed in the Dayson Island upland disposal area. Effort in FY18 includes condition surveys, plans and specifications, and award of the O&M dredging contract. The next maintenance event is scheduled for award in August 2018.

                                                                                                               United States Marine Corps Blount Island Operations and Maintenance Map