Manatee Harbor FL (C)

May 2023

FACT SHEET

Manatee Harbor, FL
Construction (C)
Congressional Districts:16

1. DESCRIPTION

The project provides a 40 feet deep by 400 feet wide entrance channel and basin, wideners at the northwest end of the entrance channel, and a turning basin 1,300 feet in diameter. The entrance channel extends approximately 3 miles from the turning basin to its intersection with the Tampa Harbor Main channel. Phase I was completed in December 1996, providing a clean entrance channel. Phase II was completed in December 2005, providing new wideners, and turning basin enlargement. Phase III was completed in 2012 and included construction of the south channel extension.

 

2. FUNDING

Estimated Total Cost $58,700,000
Estimated Federal Cost $44,900,000

     

      a. Regular Civil Works Funds:

Allocation thru FY22 $38,513,000
Allocation for FY23 $0
President's Budget FY24 $0

 

3. SPONSOR

Manatee County Port Authority
300 Tampa Bay Way, Suite I
Palmetto, Florida 34221-6608

4. STATUS

The Jacksonville District has completed a Section 156 Reimbursement Report/Integral Determination Report (IDR) for the inclusion of the Manatee County Port Authority constructed south channel extension (1590 feet long by 400 feet wide) as part of the authorized project. The IDR was approved by South Atlantic Division (SAD) in April 2019. A section 204 (f) Water Resources Development Act (WRDA) 2014 assumption of maintenance agreement was executed in December 2019 and maintenance of the south channel extension was included in the maintenance event completed in March 2020. The Jacksonville District has completed a Letter Report documenting the final accounting for all phases of the project as well as the amount recommended for reimbursement. An amendment to the Project Cooperation Agreement was executed in February 2023 to allow for reimbursement to the non-federal sponsor for the federal share of construction of the extension of the south channel.